Lifting and positioning inside an electrical station
Marraffa took care of the handling of a 57 ton transformer inside the Terna electrical station in Stornarella, in the province of Foggia.
The activity consisted of 3 main phases:
- Transformer Load on a Modular Vehicle (SPMT)
- Movement within the plant
- Unloading and positioning of the transformer
The initial phase required the lifting and positioning of the transformer on an SPMT modular vehicle using a Marraffa mobile crane, a Tadano Faun ATF 400G-6.
Subsequently, the transformer was moved within the plant using Goldhofer modular vehicles, operated by highly qualified Marraffa operators. Thanks to this advanced equipment and the experience of our operators, the transformer was moved to another area of the plant, where it was positioned with the help of the previously used mobile crane.
The excellence demonstrated by Marraffa in this complex project received the appreciation of Terna Rete Italia, the general client of the work. This recognition testifies to Marraffa's ability and commitment to providing complete and reliable logistics solutions for the sector's most complex challenges.