Exceptional heavy transport of 200 tons
Transportation of a Boiler 12.00 x 7.00 x 12.00 meters high - 200 tons.
13 December 2017
The vehicle was composed of 18 modular axles coupled in split version (12+6) and towed by two 6-axle SPMT modules (Self Propelled Modular Trailers by Goldhofer).
In order to perform the road transport, the load-bearing capacities of 2 bridges were evaluated by accredited engineering studies, because of the considerable weight of the convoy (280 tons).
During the journey, 2 teams of technicians dismantled and reconnected 4 Enel electrical lines and 1 Telecom phone line, which created obstacles to safe passage due to the height of the convoy. In addition, the dismantling of around 800 metres of guard rails and 100 metres of new concrete jerseys was planned and executed.